County continues working toward solution on Lake Oscar
Work to alleviate the overflow on Lake Oscar is ongoing. At their June 26 meeting, Douglas County commissioners approved a contract for Sellin Brothers, Inc. of Hawley to make improvements to the outlet.By: Crystal Dey, Alexandria Echo Press
Work to alleviate the overflow on Lake Oscar is ongoing.
At their June 26 meeting, Douglas County commissioners approved a contract for Sellin Brothers, Inc. of Hawley to make improvements to the outlet.
Sellin Brothers’ bid for $262,480 was 14.67 percent under the engineer’s estimate. Six other companies submitted amounts between $287,040 and $517,925.
Commissioners approved Public Works Director/County Engineer Dave Robley’s request to apply for a flood damage reduction grant with the Department of Natural Resources that will also aid efforts on Lake Oscar.
In other bid action, a construction contract was awarded to Tri-City Paving of Little Falls for maintenance of County Roads 19 and 82. The project was estimated to cost more than $1.9 million; Tri-City bid $1,410,401. Four other bids submitted ranged between $1,490,859 and $1,774,741.