The basketball hoops and volleyball nets have been installed and the acoustic panels have all been painted red in the large gymnasium at the new Alexandria Area High School. (Annie Harman/Echo Press)

School Scoop: On site at AAHS

Email Sign up for Breaking News Alerts
News Alexandria,Minnesota 56308 http://www.echopress.com/sites/default/files/styles/square_300/public/field/image/N_School_5423.jpg?itok=7_qHIsE9
Echo Press
(320) 763-3258 customer support
School Scoop: On site at AAHS
Alexandria Minnesota 225 7th Ave E
P.O. Box 549
56308

As the opening of the new Alexandria Area High School inches closer every day, the school has begun to truly take form as a place for youth to learn.

Advertisement
Advertisement
0 Talk about it

During the past three months, the site was winterized; roofing, masonry work and exterior windows were completed; and the construction crew worked on mechanical, electrical, plumbing and sheetrock.

Currently, gym equipment and lockers for the locker room are being put into place, along with auditorium stairways, tiling throughout the building, and kitchen equipment.

Painting is also being done, with 60 percent of the classroom wings being finished.

In the next couple months, the newspaper will look into the interior framing and drywall, paint, tile, ceilings, flooring, and woodwork being finished, and auditorium seating being installed.

Every Friday, the Echo Press will put together an update for the community and include a photo from the site. Check echopress.com and our Facebook page for other photos of the ongoing updates.