I-94 cable median barrier project begins June 10

Email Sign up for Breaking News Alerts
News Alexandria, 56308
Echo Press
(320) 763-3258 customer support
Alexandria Minnesota 225 7th Ave E
P.O. Box 549
56308

Motorists on Interstate 94 near Alexandria will experience intermittent lane and shoulder closures when a cable median barrier installation project begins June 10, weather permitting.

Advertisement
Advertisement

Crews will install the cable barrier along 10 miles of I-94 from mile post 96 to mile post 106.

Motorists should prepare to

slow down in areas where crews are working.

Work is expected to last about two months near Alexandria. Crews will install cable barrier in the Moorhead area beginning in late July or early August.

Cable median barrier prevents vehicles from crossing medians and hitting oncoming traffic. Installing cable median barriers in strategic locations helps prevent fatal and serious injury crashes.

Additional information about cable median barriers is available at www.mndot.gov/trafficeng/reports/cmbarrier.html.