Sealed Bids

Publish June 19, 26, 2009

ADVERTISEMENT FOR BIDS

ALEXANDRIA AIRPORT

SANITARY SEWER AND

PARKING LOT FOR MINNESOTA

Advertisement
Advertisement

ALEXANDRIA, MN

FAA AIP #: 3-27-0004-09-2009

WSN PROJECT #: 303A0258

Notice is hereby given that sealed bids will be received by the Alexandria City Council, at the Alexandria City Hall, 704 Broadway, Alexandria, Minnesota, until 9:00 a.m. on July 14, 2009 at which time all bids will be opened and read aloud for the furnishing of all materials, skill, labor and all else necessary for the 2009 Watermain Improvements project in Alexandria, Minnesota.

Major items include the following approximate quantities:

MILL BITUMINOUS PAVEMENT - 3460 SY

BITUMINOUS PAVEMENT - 620 TON

DIRECTIONAL BORE GRAVITY SANITARY SEWER - 791 LF

Notice of Requirement for Affirmative Action To Ensure Equal Employment Opportunity (Executive Order 11246)

1. The Offeror's or Bidder's attention is called to the "Equal Opportunity Clause" and the "Standard Federal Equal Employment Specifications" set forth herein.

2. The goals and timetables for minority and female participation, expressed in percentage terms for the Contractor's aggregate workforce in each trade on all construction work in the covered area, are as follows:

Time-tables: Upon Publication; Until further notice

Goals for minority participation for each trade: 2.2%

Goals for female participation in each trade: 6.9%

These goals are applicable to all the Contractor's construction work (whether or not it is Federal or federally assisted) performed in the covered area. If the contractor performs construction work in a geographical area located outside of the covered area, it shall apply the goals established for such geographical area where the work is actually performed. With regard to this second area, the contractor also is subject to the goals for both its federally involved and nonfederally involved construction. The Contractor's compliance with the Executive Order and the regulations in 41 CFR Part 60-4 shall be based on its implementation of the Equal Opportunity Clause, specific affirmative action obligations required by the specifications set forth in 41 CFR 60-4.3(a), and its efforts to meet the goals. The hours of minority and female employment and training must be substantially uniform throughout the length of the contract, and in each trade, and the contractor shall make a good faith effort to employ minorities and women evenly on each of its projects. The transfer of minority or female employees or trainees from Contractor to Contractor or from project to project for the sole purpose of meeting the Contractor's goals shall be a violation of the contract, the Executive Order and the regulations in 41 CFR Part 60-4. Compliance with the goals will be measured against the total work hours performed.

3. The Contractor shall provide written notification to the Director of the Office of Federal Contract Compliance Programs within 10 working days of award of any construction subcontract in excess of $10,000 at any tier for construction work under the contract resulting from this solicitation. The notification shall list the name, address and telephone number of the subcontractor; employer identification number of the subcontractor; estimated dollar amount of the subcontract; estimated starting and completion dates of the subcontract; and the geographical area in which the subcontract is to be performed.

4. As used in this Notice, and in the contract resulting from this solicitation, the "covered area" is (The project is in central Minnesota, Douglas County, City of Alexandria).

[43 FR 49254, Oct. 20, 1978; 43 FR 51401, Nov. 3, 1978, as amended at 45 FR 65977, Oct. 3, 1980]

Each bid must be accompanied by a certified check or a bidders bond acceptable to the Alexandria City Council in an amount of at least five (5%) percent of the total amount of the bid, payable without condition to the Alexandria City Council. In case the successful bidder fails to enter into a contract or to give bond as required by law within the specified number of days after the award of the contract, such check or bond shall be forfeited as liquidated damages.

Copies of the Plans and Specifications are on file and may be seen at the City of Alexandria, and obtained from the Engineer, at Widseth Smith Nolting & Associates, Inc., 610 Fillmore St., Alexandria, Minnesota, upon deposit of $50.00 which is not refundable.

All bids must be submitted on the official forms, prepared by the Engineer for that purpose. Bids shall be directed to the City Administrator, securely sealed and endorsed upon the outside with a brief statement as to the work for which the bid is made.

The Alexandria City Council reserves the right to hold all bids for a period of one hundred twenty (120) days after the scheduled closing time set for receiving bids and to reject any and all bids and to award the contract as the District deems in their best interest.

By Order of the

Alexandria City Council,

Alexandria, Minnesota

Jim Taddei

City Administrator

927958